How a lift is installed: the steps, in order

What happens between signing the order and riding the lift, and what your building must have ready.

  1. Site survey. We measure the shaft, pit depth, overhead height and machine room, and agree the capacity, speed and number of stops.
  2. Drawings and order. You approve the layout drawing and choose the cabin, door, ceiling, floor and handrail designs. The lift is then ordered from the factory.
  3. Civil work by the building. While the lift ships, your contractor finishes the shaft plaster, pit waterproofing, machine room slab and hoisting hook, and provides three-phase power to the machine room.
  4. Scaffolding and rails. Brackets are anchored to the shaft wall and the guide rails are aligned from pit to top.
  5. Machine and controller. The traction machine, speed governor and control panel are set in the machine room (or at the shaft head for a machine-room-less lift).
  6. Car and counterweight. The car frame, platform and counterweight are assembled in the shaft and roped.
  7. Doors. Landing doors are fitted on every floor, then the car door and operator.
  8. Wiring. Travelling cable, shaft wiring, call buttons, limit switches and safety circuits.
  9. Testing and commissioning. Slow-speed run, levelling, load test, safety gear and buffer tests.
  10. Handover. We train your caretaker and start the maintenance period.

How long it takes depends on the number of stops and how ready the shaft is. Ask us for a schedule for your building.