Do I need my own substation?

When a building in Bangladesh has to install its own 11/0.4 kV substation, and what that means for the owner.

A small house takes its supply at low tension straight from the utility's line. Once the load of a building grows past a set limit, the utility will no longer feed it at low tension. The owner has to take supply at 11,000 volts and install a private substation that steps it down to 415 volts.

The limit

The Bangladesh National Building Code says an 11/0.4 kV substation is required when the load of a building exceeds 50 kW. Your distribution company (DPDC, DESCO, BREB, BPDB, NESCO or WZPDCL) applies its own current threshold when it sanctions your load, so confirm the figure with them before you design.

Who usually needs one

  • Apartment buildings with lifts, pumps and many flats
  • Commercial buildings, hospitals, markets and schools
  • Factories and workshops of almost any size

What it involves

A substation room at ground level above flood height, an HT panel, a transformer, an LT panel, a PFI plant, earthing, and approval from the Chief Electric Inspector before the utility connects you. Our guide to the installation steps walks through the whole process.