Installing a substation in Bangladesh, step by step
From load calculation to the day the utility energises your line, including the government approvals.
- Load calculation and design. We calculate the load, size the transformer and draw the single line diagram and room layout.
- Apply to the utility. You apply to your distribution company for the new connection or load increase. For larger connections they ask for the approved building plan, the substation layout plan and the single line diagram.
- Demand note and deposit. The utility surveys the site, sanctions the load and issues a demand note for the connection fee and security deposit.
- Build the substation room. At ground level, above the highest flood level, with ventilation, cable trenches and a clear entrance.
- Supply and install the equipment. HT switchgear, transformer, LT switchgear, PFI plant, cables and earthing.
- Testing. Insulation, ratio, oil and earth resistance tests, with written test results for every item.
- Chief Electric Inspector clearance. The file goes to the Office of the Chief Electric Inspector with the government fee paid by treasury challan. An inspector visits the substation and issues the clearance certificate, commonly called the ELB certificate.
- Metering and connection. You submit the clearance and test results to the utility. They install the meter and energise the line.