Which tests does a transformer go through before delivery?

The routine and type tests in IEC 60076, what each one proves, and what to ask for in the test report.

A distribution transformer should never leave the factory untested. The international standard IEC 60076 sets out routine tests, done on every unit, and type tests, done on one unit of each design.

Routine tests, on every transformer

  • Winding resistance. Confirms the joints and conductors are sound.
  • Voltage ratio and vector group. Confirms it steps 11 kV down to 415 V correctly and is connected as Dyn11.
  • Insulation resistance. Measured with a megger between windings and to earth.
  • No-load loss and current. The power the core uses with nothing connected.
  • Load loss and impedance. The copper loss at full load and the impedance voltage, usually 4 to 6%.
  • Applied voltage test. A high voltage held for one minute proves the main insulation.
  • Induced overvoltage test. Proves the insulation between turns.
  • Oil breakdown voltage. Confirms the transformer oil is dry and clean.

Type tests, on one unit of a design

  • Temperature rise. Run at full load until temperatures settle.
  • Lightning impulse. Simulates a lightning surge on the HV winding.

What to ask for

Ask the manufacturer for the signed routine test report with the serial number of your unit. The utility and the Chief Electric Inspector will want to see it before connection. Every TOS transformer is tested in our own testing lab and delivered with its report.